Dispatch Time Definitions: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 15: | Line 15: | ||
|| Leave Plant || || || || || DepartDT in Loads Table | || Leave Plant || || || || || DepartDT in Loads Table | ||
|- | |- | ||
|| || | || || Travel Time || To Job || ARTZONETIME.TO_ZONE_MINLD || min/ld || TO_JOB_MINLD: SMALLINT<BR> | ||
|- | |- | ||
|| Arrive Job || || || || || ||Schedule Time is Anchor<BR>for Time Calculations | || Arrive Job || || || || || ||Schedule Time is Anchor<BR>for Time Calculations |
Revision as of 17:51, 7 September 2023
Time Status and Interval For Disptatch
Status Time | Interval | Dispatch Status | Default Source | Calc Method | Order Hd Field | Comment |
Ticket Time | ||||||
Batch Time | Ticketed | ARTPLANT.BATCH_SETUP_MINLD ARTPLANT.BATCH_LOAD_SECYD |
min/ld+sec/yd | BATCH_SETUP_MINLD: SMALLINT BATCH_LOAD_SECYD: SMALLINT |
BATCH_SETUP_MINYD + ((BATCH_LOAD_SECYD * {Load Size}) * 60) | |
Loaded Time | ||||||
Plant Wash | Loaded | ARTPLANT.PLANT_WASH_MINLD | min/ld | PLANT_WASH_MINLD: SMALLINT |
||
Leave Plant | DepartDT in Loads Table | |||||
Travel Time | To Job | ARTZONETIME.TO_ZONE_MINLD | min/ld | TO_JOB_MINLD: SMALLINT | ||
Arrive Job | Schedule Time is Anchor for Time Calculations | |||||
Waiting Time | Arrive | ARTPLANT.JOB_SETUP_MINLD ARTTRCLS.JOB_SETUP_MINLD |
min/ld | JOB_SETUP_MINLD: SMALLINT | ||
Begin Pour | ||||||
Pour | Pour | DITUSECL.UNLOAD_RATE_SECYD ARTTRCLS.UNLOAD_RATE_SECYD |
sec/yd | UNLOAD_RATE_SECYD SMALLINT/ INTERVAL (spacing) MINLD |
ARTORDHD.UNLOAD_RATE_SECYD should be Greater of (DITUSECL or ARTRCLS rate) --- All Resulting Time Calculations based on lesser of ARTORDHD.UNLOAD_RATE_SECYD*QTY or ARTORDHD.INTERVAL (spacing) | |
End Pour | ||||||
Job Wash | Wash | ARTPLANT.JOB_WASH_MINLD | min/ld | JOB_WASH_MINLD: SMALLINT | ||
Leave Job | ||||||
Travel Time | Return | ARTZONETIME.TO_ZONE_MINLD | min/ld | FROM_JOB_MINLD: SMALLINT | ||
Arrive Plant | ReturnDT in Loads Table | |||||
In Yard |
Time Definitions
- Target
- Times based on the load schedule time
- Projected
- Target times adjusted for the load offest (Target Return Offset). The offset is to be adjusted at each status change in the shipping process.
- Actual
- Actual times recorded